Manpower on the Gantt Chart

Follow

Overview & Background

Construction teams, especially subcontractors, often plan their work on available manpower. Including Manpower on the Gantt chart helps construction teams sequence the work that will be completed on-site. This article will help give an overview of the feature and provide examples of how the feature can be used effectively. 

How to use Manpower on Gantt

You can add manpower to Fieldwire tasks to capture the expected and actual duration of a task. 
This provides more detail-oriented information aside from the start and end dates.

_6___Replace_damaged_carpet_tile___Sample_project_-_AWH.png


How Manpower is calculated


Manpower is calculated by either Man-hours, Man-days, and Man-Months--  You can adjust these at any time under the "Project Settings" tab.

One Man-Hour  equals 1 hour
One Man-Day equals 8 hours
One Man-Month equals 30 Days 


The determination of how the manpower the tasks are dependent on the scope of the project. This will also affect how content is displayed and calculated. 

 

Navigation on the Gantt Chart

 

You can access the Gantt Chart from the 'Tasks' tab-- select the 'Gantt' view in the top-right corner. 
The default date range will be the previous, current, and next week, but you can adjust this to view other weeks. 


Tasks___Sample_project_-_AWH.png


The red, vertical line indicates Today's date.
When you hover over a task on a day, you will see a blue vertical line. The pop-up window directly above the taskbar indicates the start and end dates.

_14509___Manpower_on_Gantt_-_Google_Docs.png


In the example above, the ‘Tape & finish gyp board’ task is 30 man-hours.
30 man-hours / 8 man-hours = 3.75 man-days.
The task is from 7/27 - 8/9, or 12 days. 3.75 man-days / 12 days =
0.3 man-days each day.

On the top graph, you'll see the total manpower for all tasks that day.
The total = 0.6 + 0.3 + 0.3 + 0.8 =
2.0 total man-days.

This means that I need a minimum of two workers on-site to complete the tasks. 

More Information


Both of these articles provide more context about how to effectively schedule tasks in Fieldwire and use the Gantt view. 

Have more questions? Submit a request