Can I recreate deleted tasks after they have been deleted for more than 30 days?
Answer
If you delete a task from your project, you have the ability to restore that task from the Trash tab within 30 days of deleting it. If it has been more than 30 days and you have a premium Fieldwire account, you are able to use our built-in task importer feature to recreate any tasks that may have been deleted in error. (For more information about the task importer, check out this article: Introduction to the Task Importer).
Action 1 - Generate a CSV report of your deleted Task(s)
You can do this by going to the Tasks page and clicking the "Generate Reports" button at the top of the page. When the report template appears, complete the following steps:
Step 1: Select "CSV Report" from the available report types.
Step 2: Be sure to also select the "Deleted content" checkbox right beneath it.
Step 3: Under the Task Filters, click on the "Status" filter and select all options (P1, P2, P3, Completed, and Verified).
Step 4: Add the relevant recipients and click on the 'Send now' button on the lower right part of the box.
Action 2 - Sort and organize the CSV report data
Once you've received your report via email, you can open up the report and do the following.
Step 1: Sort by "Deleted Date" so that all of your deleted tasks are grouped together.
Step 2: If necessary, change the date format to YYYY-MM-DD (this is needed in order for our software to import the tasks correctly). You can do this by right-clicking on the cells in question, selecting "Format Cells," and then "Custom." You can then enter the YYYY-MM-DD format and save it:
Step 3: Use your cursor to select all of the rows in your deleted tasks so that you make sure you have all of the required data to recreate the tasks in your project. Then, copy the data.
Action 3 - Using the + Import Tasks feature
Step 1: Once you have copied all of that deleted task data, navigate to the top of the Tasks page in your project and click on the "Import Tasks" button. It should be right next to the "Generate Reports" button that you clicked in the beginning:
Step 2: When you see the Task Importer template open, paste the copied data from your spreadsheet report into the template, then press the blue "Import Tasks" button at the top of the template.
Note: Keep in mind you may not need all of the data from the rows/columns in the CSV to paste into the Task Importer template - make sure you check the column headers in the Task Importer template to know what data to paste where.
Tip: If you see a cell in the template highlight in red, that means you pasted incorrect data and should try again.
Note: Cells highlighted in red can also mean that you've pasted in information, such as categories or plans, that don't yet exist within the project. In these situations, make sure to add the categories, plans, etc. into the project prior to importing your tasks to resolve this problem.
If the project uses Custom Task Statuses, you’ll need to ensure that the name of the custom status matches the status entry on the task importer.
Step 3: Once you've pasted all of the necessary data into the template, click the blue "Import Tasks" button in the top right corner of the template. You should now have your deleted tasks recreated once again in your Fieldwire project.
Note: Once the task has been deleted, the contingent task number is also deleted. Even if you recreate the deleted task through the task importer, the task number of the new task will not match with the task number on the deleted task.